2015/10 - HraMoKa

Prejsť na obsah

Hlavná ponuka:

I. ETAPA > UK > RECONSTRUCTION

HRAMOKA
2015/10
 
Construction site takeover.
 
Works on furbishing theconstruction site.
 
Dismantlingof non-original construction works.
 
Removalof plastering from secondary partitions.
 
Dismantlingof original floor layers.
 
Earth work - reduction of floor gradientby removal of secondary made-up ground.
 
Dismantlingof original carpenterproducts–prison cell doors.