I. ETAPA > UK > RECONSTRUCTION

HRAMOKA
2015/12
Earth work - reduction of floor gradientby removal of secondary made-up ground.
Groundwork - cleaning of new archaeological discoveries - baroque sewage system.
Demolition work - dismantlingof fillings in holes.
Demolition work - dismantlingof secondarypartitionsof prison cells.
Earth workon storm water severs under emergency conditions.
Securing of failures in arch statics – concreting of fiddley openings in hall binding vaults.
Dismantlingdownpipes of original storm water sever.
Dismantlingcarpenterproducts–door framesof secondary created opening at the storey causing a failure in statics of the hall binding vaults.