I. ETAPA > UK > RECONSTRUCTION

HRAMOKA
2016/02
Earth work - reduction of floor gradientby removal of secondary made-up ground.
Groundwork - cleaning of new archaeological discoveries - baroque sewage system.
Demolition work - dismantlingsecondary partitions of prison cells.
Demolition work - dismantlingof original ceramic pavement and floor finish.
Earth work on storm water severs under emergency conditions.
Dismantlingof originalstorm water sever.
Earth work – excavation of foundation pit for sink.
Installationof casing in excavation pit.
New discoveries in archaeological research – agricultural storage structure in the courtyard, underground spaces originating from the renaissance rebuilding of the castle.
Restauration work onrenaissance – baroque pillars.
Preparation for final documentation of the archeologic discovery site byorthophotogrammetry.