2016/03
Excavation anddemolition works on waste water sewage –excavation of construction pit for dump in ledge rock.
Earth workon storm water sewage–excavation for storm water sewage in the hall.
Installationof storm water sever.
Pressure tests.
Installationbrick coverage of sewage pipes.
Excavation anddemolition workson waste water sewage–excavation for placing waste water pipes in the hall´s ledge rock.
Brickwork- final walling of the baroque sewage for leading the pipes of the floor ventilation system in the hall.
Brickwork- walling of openings (doors).
Restauration work onrenaissance – baroque pillars.