I. ETAPA > UK > RECONSTRUCTION

HRAMOKA
2016/05
Finishing work on sewage.
Installationof casingforground slab of the dump.
Concretingthe traverseslabof the dump.
Installationcasingfor filling inof the dump.
Filling in the floors with crushed gravel.
Adaptationof foundation layers in the hall.
Installationof floor ventilation system in the hall in the route of original baroque channels.
Demolition work–demolition ofwindow niches.
Brickwork- correction of walls and plasters.